Spring and Cannon Streets resurfacing delayed due to weather

Charleston, S.C.—Due to the forecast of rain and cold temperatures this week, the resurfacing of Spring and Cannon Streets originally scheduled to begin tomorrow, Dec. 6th, will now be scheduled to begin on Dec. 11th. At that time, work will begin at Spring and Meeting Streets and, weather permitting, will follow the work plan outlined below:

  • Monday, Dec. 11:
    • No parking on Spring Street.
    • Spring Street: Milling south side.
  • Tuesday, Dec. 12:
    • No parking on both Cannon and Spring Streets.
    • Spring Street: Paving south side.
    • Cannon Street: Milling north side.
  • Wednesday, Dec. 13:
    • No parking on Cannon Street.
    • No parking on Spring Street.
    • Spring Street: Milling north side.
    • Cannon Street: Paving north side.
  • Thursday, Dec. 14:
    • No parking on Spring Street until pavement markings are in place. It is anticipated that most of Spring Street parking will be available by the end of the day Thursday.
    • No parking on Cannon.
    • Spring Street: Paving north side.
    • Cannon Street: Milling south side.
  • Friday, Dec. 15:
    • Cannon Street: Finish milling south side. Begin paving south side.
    • No parking on Cannon until pavement markings are in place.
    • Spring complete. Intersection work may be completed as needed.
  • Saturday, Dec. 16:
    • Cannon Street: Finish paving south side. Intersection work may be completed as needed.
    • No parking on Cannon within work zone. As pavement markings are installed, parking will be opened.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s